More renewable energy from hydropower: Refurbishment work at an altitude of 1,700 metres

  • Doubling the storage capacity makes the region’s energy supply more flexible
  • Efficient implementation of the energy infrastructure project through work on existing infrastructure

STRABAG is refurbishing the Wurtenspeicher reservoir in Austria for energy provider Kelag. The project will almost double the reservoir’s capacity, increasing its volume from 2.7 million to 5 million cubic metres – roughly equivalent to 2,000 Olympic-sized swimming pools. 
By storing water when electricity is plentiful and generating power when demand rises, reservoirs like the Wurtenspeicher help to balance the grid and strengthen the supply of renewable energy in southern Austria. 

  • High-performance storage systems are key to the success of the energy transition. Together with Kelag and drawing on our experience in high-altitude and hydraulic engineering, we have driven forward the development of a reliable and sustainable energy supply in the region through the expansion of the Wurtenspeicher dam.

    Franz Redl
    Member of the Executive Board of STRABAG AG Austria
  • The Wurtenspeicher plays a key role for the Fragant power station group. By almost doubling the storage volume to 5 million cubic metres, we are significantly increasing the flexibility of our generation whilst at the same time strengthening security of supply. The project is a vital component of a sustainable and future-proof energy system. With an investment of around 30 million euros, we are creating additional storage capacity for the efficient use of renewable energy.

    Reinhard Draxler
    Kelag Executive Board

Work on existing infrastructure

The circumstances for the development projects in the Alps are demanding for the STRABAG groups, in terms of organisation and because of challenging terrain. Some of the heavy construction equipment had to be transported along a narrow road with a gradient of over 10 per cent.  
In total, STRABAG produced and installed 246 large-diameter bored piles in record time. The piles are positioned close together and extend up to 25 metres into the ground, requiring the team to work with centimetre-level precision. An additional protective plank seals the dam securely against scouring. Using the existing energy infrastructure enables faster expansion of the existing infrastructure.

Adaptations to the new water level

A total of 230,000 m³ of material was excavated from the quarry at the base of the dam and used to build up the Wurtenspeicher. Numerous structures must be adapted to the new water level of the Wurten reservoir as a result of the dam raise. STRABAG is also refurbishing the valve chamber, which controls the water supply, and the spillway funnel. 
 
In order to carry out the expansion work, the Wurten reservoir had to be completely emptied twice: once last year and again at the beginning of this year. The reservoir had to be refilled before winter set in to prevent damage to the dam. Thanks to close collaboration between STRABAG Civil Engineering and ZÜBLIN Specialised Civil Engineering, the first phase of the works was completed in December 2025. To ensure completion on schedule, the team worked additional shifts, including nights. 
The Wurtenspeicher reservoir forms part of Kelag’s Fragant hydropower scheme in the Möll Valley. This scheme comprises 15 reservoirs and headwater channels totalling around 79 km in length, as well as 10 power stations. Together, these facilities generate around 800 million kilowatt-hours of electricity each year, which is equivalent to the annual consumption of around 225,000 households. 
STRABAG Group
STRABAG AG Austria & ZÜBLIN Specialised Civil Engineering
Client
Kelag
Location
Fragant Power Station Complex, Innerfragant/Mölltal
Start of construction
Spring 2025, completion of the main works in 2026
Storage capacity
2.7 million to date; 5 million in future
Raising the reservoir’s maximum water level
8.5 m
Bulk material
230,000
Workers on the building site
Around 70 people
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag

The Wurtenspeicher is the centrepiece of Kelag’s Fragant power station complex in the Mölltal valley, at an altitude of 1,700 metres above sea level

jpg ∙ 2 MB
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag

The dam will be raised by seven metres, thereby almost doubling its storage capacity from 2.7 to 5 million cubic metres of water.

jpg ∙ 847 KB
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag
Aerial view of the Wurtenspeicher reservoir in Carinthia © kelag

The dam will be raised by seven metres, thereby almost doubling its storage capacity from 2.7 to 5 million cubic metres of water.

jpg ∙ 2 MB
Photo of the project team at the Wurtenspeicher © kelag
Photo of the project team at the Wurtenspeicher © kelag

In the photo, from left to right: Reinhard Draxler (Kelag Executive Board member); Mario Körbler (Kelag project manager); Franz Redl (member of the Executive Board of STRABAG AG Austria); Christian Rupp (Head of Generation at Kelag); Maximilian Rutar (STRABAG project manager).

jpg ∙ 868 KB

STRABAG AG is Austria’s leading construction company and part of STRABAG SE, acting as the parent company of the Austrian STRABAG subsidiaries. As a technology group for construction services, our activities span all areas of the construction industry and cover the entire construction value chain. We create added value for our clients by taking an end-to-end view of construction over the entire life cycle – from planning and design to construction, operation and facility management to redevelopment or demolition. In all of our work, we accept responsibility for people and the environment: We are shaping the the future of construction. As Austria’s largest construction company, we generate an annual output of around € 2.9 billion with approximately 12,835 employees.
Working together with strong partners, we are pursuing a clear goal: to design, build and operate construction projects in a way that protects the climate and conserves resources. More information is available www.strabag.at