Out-of-court settlement over North-South Cologne Stadtbahn project

  • Disputes settled over collapse of the city archive building on 3 March 2009: consortium consisting of Bilfinger SE, Wayss & Freytag Ingenieurbau AG and Ed. Züblin AG reaches settlement with the City of Cologne and Kölner Verkehrs-Betriebe AG (KVB)
  • City of Cologne’s claims settled by payment of € 600 million
  • Portion attributable to the STRABAG SE Group largely covered by insurance and risk provisions – no impact on earnings estimate for 2020

Vienna, 29 June 2020---The City of Cologne, Kölner Verkehrs-Betriebe (KVB) and the consortium Nord-Süd-Stadtbahn Köln Los Süd, in which the STRABAG subsidiary Ed. Züblin AG has a one-third stake, have agreed on an out-of-court settlement of the civil lawsuits over the collapse of the Cologne city archives on 3 March 2009. All claims will be settled by payment of a total of € 600 million by the consortium. Under the settlement agreement, the consortium has also agreed to carry out, at its own expense, the refurbishment and extended completion of the structural shell of the track switching facility as well as the integration of a space for a future memorial.

The STRABAG SE Group’s proportionate share of the settlement amounts to € 200 million. Due to insurance coverage and corresponding risk provisions, the agreement will not impact the earnings estimate of the publicly listed STRABAG SE Group for the 2020 financial year.

The agreement helps to avoid another long legal dispute about the cause and amount of damage, which would tie up material and human resources. Despite the fact that the cause of the damage has not been conclusively clarified, the consortium has agreed to discontinue the reconnaissance inspections at the accident site. This clears the way for the refurbishment and completion of the track switching facility and the conclusion of the underground line.

The Management Board of STRABAG SE welcomes the settlement, which averts a further long phase of uncertainty. “In view of the extremely complex issue regarding the cause of the damage, which has kept all involved parties occupied for more than 11 years and would probably have kept them occupied for another 10 to 15 years, and after intensive consideration of all options, we consider the agreement reached to be reasonable – not only for all project participants but also for our shareholders,” says Thomas Birtel, CEO of STRABAG SE and Chairman of the Supervisory Board of Ed. Züblin AG. “The time has come to draw a line under the past and to focus on the challenges facing us in these difficult times. Still, the third of March 2009 will remain a deeply tragic day that we will never forget.”

Download Press Kit as ZIP Download

Download Press Release as PDF Download

STRABAG SE is a European-based technology group for construction services, a leader in innovation and financial strength. Our activities span all areas of the construction industry and cover the entire construction value chain. We create added value for our clients by taking an end-to-end view of construction over the entire life cycle – from planning and design to construction, operation and facility management to redevelopment or demolition. In all of our work, we accept responsibility for people and the environment: We are shaping the future of construction and are making significant investments in our portfolio of more than 250 innovation and 400 sustainability projects. Through the hard work and dedication of our approximately 86,000 employees, we generate an annual output volume of around € 19 billion.
Our dense network of subsidiaries in various European countries and on other continents extends our area of operation far beyond the borders of Austria and Germany. Working together with strong partners, we are pursuing a clear goal: to design, build and operate construction projects in a way that protects the climate and conserves resources. More information is available at www.strabag.com.